Nscale, an artificial-intelligence infrastructure company with roots in Bitcoin mining, has filed for an initial public offering in New York after rapidly expanding from powered land and data centers into GPU compute, energy infrastructure and AI software.
The company filed its Form S-1 with the U.S. Securities and Exchange Commission on September 18 and plans to list on the New York Stock Exchange under the ticker NSCL. The filing does not yet specify the number of shares to be sold or an offering price.
Nscale grew out of Bitcoin mining infrastructure
Nscale’s history makes the filing especially relevant to the Bitcoin mining industry. According to its SEC registration statement, the business began assembling powered land in low-cost energy markets in 2022 and 2023 while it was still part of Arkon Energy. Nscale was spun out from Arkon in May 2024.
The transition illustrates a broader connection between Bitcoin mining and AI infrastructure. Both businesses require access to large quantities of electricity, data-center construction, cooling, networking and the ability to deploy specialized computing hardware at scale. Those similarities have encouraged several companies with mining backgrounds to pursue AI and high-performance computing.
Revenue surges while spending remains enormous
Nscale reported revenue of approximately $140.6 million for the six months ended June 30, 2026, compared with $10.4 million during the same period a year earlier. Reuters calculated that as a 1,252% year-over-year increase.
Growth has come with substantial costs. Nscale reported a net loss of approximately $1.02 billion for the first half of 2026, compared with a $368.9 million loss in the comparable 2025 period. Those figures show the capital intensity involved in building large AI campuses, acquiring GPUs and securing power infrastructure.
Power has become the central resource
Nscale’s filing repeatedly emphasizes electricity. The company says access to reliable, contiguous power has become a primary constraint on AI infrastructure deployment. Its strategy therefore resembles an industrial infrastructure business as much as a conventional cloud company.
Nscale says it operates across 14 regions and has a power pipeline exceeding 10 gigawatts. In March 2026 it acquired American Intelligence & Power Corporation, including the Monarch Compute Campus in Mason County, West Virginia. Nscale says the campus has a development runway scalable beyond 6.5 GW of IT load power and more than 8 GW of gross power.
The company subsequently created Nscale Energy & Power to bring power origination and development capabilities directly into the organization.
More than $100 billion in contracted value
Nscale says its total contracted value has expanded beyond $103 billion. Reuters reports that Microsoft and Anthropic are expected to become major customers, while an Anthropic agreement tied to the West Virginia campus is valued at roughly $45 billion.
The scale also creates concentration risk. Reuters reported that Nscale’s largest customer accounted for 52% of first-half 2026 revenue. The company’s SEC filing also describes substantial financing requirements and development milestones associated with some major contracts.
From mining hardware to full-stack AI
Nscale is moving beyond physical infrastructure. In July it entered an agreement to acquire Anyscale, the company built by the creators of the open-source Ray distributed-computing framework. Nscale says Ray has accumulated approximately 740 million downloads.
The planned combination would connect power generation, liquid-cooled data centers and GPU clusters with a software layer used to distribute AI workloads. In other words, infrastructure expertise that began around powered sites is moving progressively higher through the computing stack.
Bitcoin mining’s infrastructure expertise is becoming valuable elsewhere
Nscale is an unusually clear example of how expertise developed around cryptocurrency mining can transfer into another compute-intensive industry. Bitcoin miners learned to locate inexpensive electricity, build high-density computing facilities, manage cooling and deploy specialized machines in large quantities. AI infrastructure requires many of the same physical disciplines, although the hardware, networking, reliability requirements and customer economics differ substantially.
The IPO filing does not guarantee that the offering will be completed, and its final valuation has not been established. But Nscale’s path from Arkon Energy to a proposed NYSE listing demonstrates how valuable access to power and data-center infrastructure has become during the AI buildout.
Sources: Nscale Form S-1 filed with the U.S. Securities and Exchange Commission; Reuters.