South African colocation operator Teraco reported on November 17 that contracted wind electricity began reaching its Cape Town data centers through existing utility networks in September. Its separate Sediba photovoltaic development in the Free State is nearing completion. The combination demonstrates a practical way for computing operators to commission renewable supply without locating every server beside a generator.
The wind milestone concerns electricity procurement already underway, whereas the 120 MW solar plant remains under construction. Teraco expects grid energization in December 2026, followed by commissioning and generator compliance tests in early 2027. The distinction matters because generating equipment cannot be treated as a dependable source of power before electrical acceptance and operational testing.
Moving renewable power through the grid
Wheeling uses transmission and distribution infrastructure to move contracted electricity between producers and consumers. The physical grid continuously balances all connected generation and demand; the commercial arrangement allocates contracted energy using metering and settlement rules. A data center therefore remains dependent on network reliability even when its annual electricity purchases are predominantly renewable.
Sediba’s developer projects 354 GWh of annual output. Dividing by 120 MW multiplied by 8,760 hours yields an implied capacity factor of approximately 33.7%, using the announced capacity as the denominator. The figure is a forecast rather than measured production, and its interpretation depends on the AC or DC rating boundary. Average annual generation would be approximately 40.4 MW.
Complementary generation and grid capacity
Wind production can extend into hours when photovoltaic output is unavailable, reducing the mismatch between daytime solar generation and continuously operating servers. The actual benefit depends on the correlation between hourly wind and solar output and the facilities’ consumption profiles. A combined portfolio is not equivalent to a guaranteed firm supply.
Teraco also reports financing a 500 MVA switching station upgrade at Eskom’s Scafell substation, with 380 MVA available for other renewable projects. Apparent power in MVA is not identical to active power in MW; the conversion depends on power factor and network operating limits. Grid reinforcements can benefit customers beyond the original project, provided other generators secure their own connections and approvals.
The approach differs from the Norfolk solar and storage proposal, the Nova Scotia wind-powered AI proposal, the Swedish hydropower-oriented campus and Digital Realty’s Illinois campus. The next evidence to watch is completed Sediba commissioning, metered annual generation, hourly renewable matching and the actual reliability of wheeled electricity. Those measures will show whether additional computing demand can be accommodated alongside new generation rather than merely transferring electricity demand to an already constrained network.