Two 1,680-Ton Machines Begin Digging Parallel Rail Tunnels for the $16 Billion Hudson Project

Green cutterhead of the Palisades tunnel boring machine during factory testing

Two enormous excavation machines are now advancing through the New Jersey Palisades as part of the $16 billion Hudson Tunnel Project. The November 20, 2026 contractor announcement confirms that excavation of the southern rail tube began in November, following the northern machine’s October launch. The parallel operations mark a construction milestone for a new railway connection between New Jersey and Manhattan, although the machines have not yet reached the section beneath the Hudson River.

Two tunnel boring machine assemblies at the Palisades construction site
Parallel tunnel boring machine assemblies in the Palisades launch area. Credit: Gateway Development Commission, via Construction Dive.

Two underground factories

The Gateway Development Commission’s technical overview identifies each machine as weighing 1,680 tons, with a rotating cutting face measuring 28 feet 8 inches across. Their trailing equipment extends approximately 500 feet. Rather than simply drilling a hole, each single-shield machine excavates rock while supporting the installation of the permanent concrete tunnel lining.

Disc cutters concentrate mechanical force against the rock, producing fractures as the cutterhead rotates. Hydraulic systems advance the machine, while conveyors and supporting equipment remove excavated material. Behind the cutting face, precast concrete segments are assembled into rings. Engineers must coordinate the rate of excavation, material transport and lining assembly so that delays in one operation do not halt the entire process.

A circular excavation with a diameter of 28 feet 8 inches has a theoretical cross-sectional area of approximately 645 square feet. Over the planned 5,100-foot length of one tube, that corresponds to roughly 3.29 million cubic feet of in-place rock, or 122,000 cubic yards. Both tubes together represent approximately 244,000 cubic yards before accounting for cross passages, excavation tolerances or the expansion of broken rock.

Constructing beneath a dense urban corridor

The finished internal diameter will be 25 feet 2 inches, allowing space within the excavated envelope for permanent lining and associated construction requirements. Six connecting passages are planned between the two tubes. At the eastern end of the Palisades package, a shaft approximately 120 feet deep will provide access for machine removal. Similar spatial and construction constraints arise in Cambridge’s underground electrical substation and the Propel NY transmission project.

Hudson Tunnel Project route and construction packages
Planned rail alignment and construction packages between New Jersey and New York Penn Station. Credit: Gateway Development Commission, via Construction Dive.

According to Construction Dive’s November 19 reporting, the northern machine had excavated about 400 feet and installed more than 60 lining rings. The river crossing will require a different pair of machines suited to its ground conditions. Boring beneath the Hudson is planned to begin in 2028.

Replacing a century-old dependency

The existing North River Tunnel entered service in 1910. Building an additional connection will allow rehabilitation of the aging infrastructure while providing greater redundancy. Rail capacity also depends on signaling, electrical supply, track connections and station operations. Comparable system-level engineering challenges appear in our coverage of Britain’s new high-voltage infrastructure and NASA’s large mechanical research facility. The next measurable milestones are excavation progress, shaft completion and subsequent deployment of the river-crossing equipment.

Cover photograph: tunnel boring machine S-1432 during factory testing. Credit: Gateway Development Commission.

We volunteer daily to ensure the credibility of the information on this platform is Verifiably True. If you would like to support to help further secure the integrity of our research initiative, please scan the QR code below.

Bitcoin donation QR code
Support independent research with 5,000 satoshis.

BitcoinVersus.tech is not a financial advisor. This media platform reports on financial subjects purely for informational purposes.

Leave a Reply