Cipher’s 207 MW Odessa Bitcoin Mine Produces 296 BTC in Q3 at 2.8¢/kWh Power Cost

Cipher executives discussing mining and HPC strategy in a historical interview

Cipher Digital’s remaining Bitcoin mining operation in Odessa, Texas, produced approximately 296 BTC during the third quarter of 2026. The company’s November 2 investor presentation, filed with the U.S. Securities and Exchange Commission, identifies 207 MW of total electrical capacity, approximately 11.6 EH/s of hashrate, a fleet efficiency of 17.2 J/TH and an electricity cost of about 2.8 cents per kilowatt-hour. Odessa remains an operating mine while Cipher develops infrastructure for high-performance computing customers.

Historical Cipher management Q&A on second-quarter 2025 results, including Odessa uptime. The video predates the current filing.
Cipher Digital investor slide with aerial Odessa site photo and reported operating metrics
Source: Cipher Digital Q3 2026 presentation, slide 13, filed November 2. Company-reported capacity, hashrate, efficiency and electricity cost.

The site’s 296 BTC compares with approximately 346 BTC in the second quarter of 2026, a decrease of about 14.5%. The two presentations report the same headline hashrate and fleet efficiency. That does not establish identical average pool-side hashrate, uptime or network conditions across both quarters. Bitcoin production depends on the facility’s effective computational contribution relative to the network and the rewards distributed over the measurement period. Recent network difficulty changes illustrate the changing competitive environment.

Zero-baseline columns comparing approximately 346 BTC mined in Q2 2026 and 296 BTC in Q3 2026, a 14.5 percent decline. Reported site metrics: 207 MW, 11.6 EH/s, 17.2 J/TH and 2.8 cents per kWh.
Odessa quarterly Bitcoin production, Q2–Q3 2026. Source: Cipher Digital SEC-filed business updates dated August 4 and November 2. Approximate reported output fell by 50 BTC, or 14.5%. Site capacity, hashrate, fleet efficiency and electricity cost are separately annotated and not measured on the BTC axis.

Power economics at the machine boundary

Multiplying 11.6 EH/s by 17.2 J/TH implies approximately 199.52 MW of equipment power if both figures describe the same simultaneous operating condition. The calculation leaves a mathematical difference of 7.48 MW from the stated 207 MW site capacity. That difference is not verified spare electrical capacity: cooling, distribution losses, operating margins and the measurement boundary must be considered. Our analysis of nameplate and facility-level efficiency explains why equipment ratings cannot automatically be treated as metered power.

At the reported 2.8¢/kWh rate, one continuously operating petahash per second at 17.2 J/TH would consume 412.8 kWh per day, equivalent to approximately $11.56 in energy charges. That is a simplified electricity-only model, excluding overhead, maintenance, depreciation, financing and potential curtailment.

Revenue, costs and flexible electricity consumption

Cipher’s quarterly report attributes approximately $20.8 million in mining revenue to Odessa and identifies $14.6 million in mining cost of revenue, primarily electricity. Dividing the latter by the rounded output gives approximately $49,324 per BTC. The ratio is a reported cost-of-revenue measure, not a fully allocated production cost. Cipher separately reported $4.3 million in proceeds from selling excess contracted electricity through Luminant during the quarter. Electricity resale offers an alternative use for contracted power when market conditions warrant, rather than an additional block reward.

Cipher executives Tyler Page and Chris Totin discuss mining infrastructure and HPC strategy in an earlier industry interview; not the November 2026 earnings call.

The company continues to explore HPC monetization at Odessa. Its earlier Barber Lake expansion and the industry’s Québec mining-to-HPC conversion plans illustrate competing uses for energized infrastructure. No new Odessa HPC lease was established by the November site snapshot. The existing mine’s reported production, power agreement and actual quarterly expenses provide a more useful operating benchmark than speculative conversion capacity.

We volunteer daily to ensure the credibility of the information on this platform is Verifiably True. If you would like to support to help further secure the integrity of our research initiative, please scan the QR code below.

BitcoinVersus.Tech donation QR code for 5,000 satoshis