XTX Markets Opens 22.5 MW Finnish Data Center After Moving 417 PB of Storage Capacity

XTX Markets first Finnish data center at Kajaani.

Algorithmic trading company XTX Markets opened its first wholly owned data center in Kajaani, Finland, on November 24, 2026. The company announcement identifies 22.5 MW of IT power capacity and a 15,000-square-meter building within a 193-hectare campus. The facility houses computing infrastructure for financial forecasting with machine learning. Unlike the proposed Alaska Arctic computing campus, the first Kajaani building has reached opening.

Moving hundreds of petabytes

According to XTX and Data Center Dynamics’ November 25 report, a six-week stage of the relocation transferred equipment representing 417 PB of storage capacity: 385 servers containing 17,000 drives and weighing approximately 26 tonnes. The hardware traveled from a leased facility about five kilometers away. Storage capacity is not necessarily the volume of unique live data transferred, and the reported physical relocation should not be confused with a network transfer benchmark.

Moving equipment without interrupting research requires coordinating dependencies between storage volumes, compute nodes and network services. A staged migration can preserve service availability through redundancy and workload placement while equipment is disconnected and brought online elsewhere. Those are general engineering techniques; XTX did not disclose its full implementation. Dense storage systems such as the Supermicro petascale flash platform illustrate the volume of data that can be concentrated within individual servers.

The company’s announcement includes a video case study of its storage migration. The full project involved more than the reported six-week stage.

Power and cooling boundaries

Official aerial photograph of the broader Kajaani campus
XTX Markets’ official campus overview photograph, November 24 announcement.

XTX reports no consumptive water use for cooling at the facility. That does not mean the site has no water use of any kind or that cooling has no energy cost. The electrical power required by fans, pumps and other auxiliary systems must be considered separately from the stated IT rating. At continuous full IT capacity, the arithmetic energy equivalent of 22.5 MW is 197.1 GWh over 8,760 hours. Actual energy consumption depends on utilization and facility overhead, as demonstrated by the distinctions between contracted electricity and delivered energy in Sabey’s Texas power procurement agreement.

Expansion depends on grid access

The second building is scheduled to open in 2027. XTX says electricity arrangements are secured for the first two facilities, while the third, under construction for a mid-2028 target, faces uncertainty associated with power-line permitting. Finnish public broadcaster Yle also reported the company’s concerns. The operator reports investing more than €400 million in construction and employing more than 30 permanent staff in Kajaani. The power constraint echoes the broader challenge of coordinating compute deployment with electrical infrastructure, examined in our Homer City energy campus report.

The current milestone is one operational facility, not completion of the entire planned campus. Future expansion depends on construction, electrical connection, commissioning and confirmed operating requirements. The distinction is important for estimating regional power demand and evaluating the reliability of proposed computing capacity.