Sabey Data Centers has entered a decade-long virtual power purchase agreement tied to the operating Greasewood solar farm in Pecos County, Texas. In its November 17, 2026 announcement, Sabey disclosed contracted solar capacity of 43.5 MW and estimated annual production of 130 GWh. The agreement supports renewable electricity procurement rather than establishing a dedicated electrical connection between the solar farm and Sabey’s computing facilities. A different approach to utility-scale renewable infrastructure is described in our California Valley Solar Ranch coverage.

An existing 255 MW solar installation
According to original developer OnPeak Power, Greasewood entered commercial operation in February 2021 with 255 MW of alternating-current generating capacity. Copenhagen Infrastructure Partners acquired the project site in 2018. Electricity enters the ERCOT grid. Sabey’s contracted 43.5 MW represents approximately 17.1% of the plant’s stated AC capacity, assuming comparable rating bases. No new generating equipment is announced under the agreement.
Capacity is not continuous generation
A hypothetical generator operating at 43.5 MW for every hour of a 365-day year would produce 381.06 GWh. Dividing the expected 130 GWh by that theoretical maximum gives an indicative capacity factor of 34.1%. The same annual energy divided by 8,760 hours corresponds to approximately 14.84 MW of average power. Neither figure guarantees delivery at any particular hour. Over ten years, constant annual production at the estimated level would total 1.3 TWh, before accounting for actual weather, degradation and curtailment.

Solar output depends on irradiance and equipment availability. Storage can shift energy between hours, as illustrated by Utah’s Faraday battery project. However, Sabey did not announce a battery as part of the Greasewood contract. Computing facilities must still obtain dependable electricity when renewable generation declines.
What a virtual power purchase agreement actually supplies
A virtual power purchase agreement generally separates commercial settlement and renewable energy attributes from physical electricity delivery. The generator sells energy into the electricity market, while the contractual counterparties settle according to their agreed terms. The customer’s facility continues to procure its physical electricity separately. Data Center Dynamics subsequently clarified that Sabey is not directly receiving Greasewood electricity. The company has not disclosed the agreement’s financial settlement price.
That distinction separates the deal from generation infrastructure such as Homer City’s planned gas-powered AI campus. A virtual contract alone does not provide electrical redundancy, backup generation or additional firm interconnection capacity at a data center.
Implications for data center energy procurement
Sabey reported a 29.3% reduction in market-based Scope 1 and Scope 2 emissions against its 2018 baseline in its 2025 sustainability reporting and targets net-zero emissions across those scopes by 2029. Annual renewable energy accounting is distinct from hourly clean electricity matching. The continuing development of alternative grid-scale storage technologies illustrates one potential route toward greater temporal flexibility. Greasewood’s significance is a long-term commercial commitment to existing renewable generation, not a new 43.5 MW round-the-clock supply for servers.
Featured photograph: Sabey Data Centers, supplied with its November 17, 2026 announcement.
We volunteer daily to ensure the credibility of the information on this platform is Verifiably True. If you would like to support to help further secure the integrity of our research initiative, please scan the QR code below.

For mobile scanning, open the article on another display and scan the QR code with a Bitcoin wallet. The voluntary donation amount is 5,000 sats. Verify the receiving address 3C9o19EH5HSiwEPyCTmEKzxhNCbo2X6TTb before sending.
BitcoinVersus.tech is not a financial advisor. This media platform reports on financial subjects purely for informational purposes.

Leave a Reply