A portion of a hydroelectric-powered Bitcoin mining facility in Joliette, Québec, now serves customers running artificial intelligence applications. In its November 23, 2026 announcement, SATO Technologies reported that subsidiary Qritical AI had secured its first AI colocation customer, Datum Technology. The customer installed NVIDIA B300 GPU servers inside a secured section of the existing facility.

The development is more concrete than a proposed conversion or a preliminary power agreement. SATO reports a completed initial installation serving end customers, although neither the number of accelerators nor the electrical capacity assigned to the new deployment has been disclosed.

For technical context, CoreWeave’s HGX B300 engineering video shows a separate deployment of Blackwell Ultra technology. It does not document the Joliette installation.

From a signed agreement to customer service

The companies signed their initial agreement on October 21. SATO delivered the prepared space to Datum on November 12, and Datum made the infrastructure available to its customers on November 16. The elapsed periods were 22 days from agreement to facility handover, followed by four more days to customer delivery. The combined period was 26 days.

Existing power distribution, buildings and personnel can shorten portions of a development schedule. The reported timeline does not include all earlier planning, equipment procurement or the original construction of the mining facility. It should not be interpreted as a general construction benchmark for a new hyperscale data center.

Why GPUs and ASICs require different infrastructure

Bitcoin ASICs perform a narrow hashing workload, whereas GPUs execute a broader range of mathematical operations. AI applications can require substantial memory bandwidth, communication among processors and storage throughput. NVIDIA’s Blackwell Ultra architecture overview describes 288 GB of high-bandwidth memory per GPU. A hypothetical eight-GPU configuration would therefore contain 2,304 GB of aggregate GPU memory, although individual applications need appropriate software and communication mechanisms to use memory distributed across multiple accelerators.

ASUS reference B300 server topology
ASUS B300 reference server topology. Datum’s exact server model and network configuration were not disclosed.

The conversion also requires careful assessment of cooling, rack loading, grounding, network cabling and electrical protection. Mining equipment does not become AI hardware merely because both workloads operate within the same building. SATO has not disclosed the detailed engineering modifications undertaken for Datum.

Twenty megawatts is the site capacity

The facility has 20 MW of connected hydro-powered capacity, according to SATO’s corporate overview. A continuous site-wide draw at that level would consume 480 MWh daily or 175.2 GWh annually. Neither figure is a measured consumption total. Bitcoin mining continues elsewhere at the property, meaning the full 20 MW cannot be attributed to AI.

Datum owns and operates its computing equipment; Qritical AI supplies facility resources and local support. Contract economics remain confidential, preventing an assessment of revenue per megawatt or profitability. The November 25 Data Center Dynamics report independently covers the development.

A measurable milestone, with limits

Related developments include Abits’ Tennessee hosting evaluation, CleanSpark’s Georgia expansion plans, Applied Digital’s 25 MW hall delivery and Bitdeer’s electrical equipment delays. For SATO, subsequent customer agreements, allocated IT capacity and documented operating performance would help establish how far the conversion can scale.

Featured image: NVIDIA’s Blackwell Ultra reference platform. The image depicts relevant technology, not the actual Datum installation.

We volunteer daily to ensure the credibility of the information on this platform is Verifiably True. If you would like to support to help further secure the integrity of our research initiative, please scan the QR code below.

Optional research support QR code

2 responses to “Québec Bitcoin Mine Brings NVIDIA B300 AI Servers Online in 26 Days”

  1. […] a computing campus. Comparable infrastructure transitions covered by BitcoinVersus.Tech include Québec’s Bitcoin mine conversion, Applied Digital’s commissioned 25 MW hall, the Qatar 20 MW groundbreaking and Google’s […]

    Like

  2. […] architecture, MemryX’s multi-chip accelerator, Ezurio’s edge inference module and SATO’s GPU deployment. HyperAccel’s next meaningful milestone would be independently reproducible benchmarks under […]

    Like

Leave a Reply