A former coal-fired power station in California could acquire a third industrial identity: a biomass-powered artificial intelligence factory. NewYork GreenCloud has submitted a conditional-use permit application for a 14.4 MW data center at the Buena Vista Biomass Power facility near Ione, according to November 24 reporting by Data Center Dynamics. The filing concerns a proposed facility rather than commissioned computing capacity.
The developer acquired Buena Vista in January. Its acquisition announcement outlined a longer-term plan to raise the power station’s capacity from 18 MW to 41 MW. The existing facility was converted from coal to biomass in 2009. The featured photograph is an archival view published in 2016 by KVPR, credited to Andrew Nixon of Capital Public Radio, not a depiction of operating AI equipment.
From forest residues to GPU electricity
The permit application describes a roughly 13,000-square-foot building, closed-loop cooling and electricity supplied directly by the plant. Behind-the-meter generation can reduce dependence on new utility capacity, but reliable service still requires coordinated generators, switchgear, protection systems, backup supply and cooling equipment.

The proposed redevelopment also incorporates pyrolysis, a process in which organic material is heated under oxygen-limited conditions. Depending on process design, the resulting gases and liquids can provide energy while some carbon remains in solid biochar. Net carbon removal depends on feedstock sourcing, transportation, process emissions, biochar stability and end use. NewYork GreenCloud’s carbon-negative description remains a company claim, not an independently established lifecycle result.
The 2,304-GPU contract is not yet a deployment
A separate October 29 disclosure by server manufacturer 2CRSi clarifies that a contract covering 288 servers and 2,304 NVIDIA B300 GPUs had not been activated. Activation depends on power-plant restart, permits, financing, full payment arrangements and at least 5 MW of firm power at the computing facility. The vendor also reported that its customer attributed recommissioning delays to pipeline leaks.
Consequently, readers should distinguish the 14.4 MW permit application, the existing plant’s historical 18 MW rating, the 41 MW redevelopment ambition and the conditional server agreement. Each measures a different aspect of the project.
Engineering and environmental milestones
A continuous 14.4 MW facility load would consume approximately 126.1 GWh per year before any changes in utilization. The implied energy demand makes fuel procurement, maintenance outages and emission controls consequential. Closed-loop cooling can reduce evaporative demand compared with conventional cooling towers, but does not eliminate every water requirement.
A November 24 community submission raised environmental-review questions; it is an advocacy document, not a county determination. Planning approval, verified financing, measured generation and actual GPU commissioning remain the milestones to watch.